HIGHWAY RECONSTRUCTION: Week of March 23

With the new traffic shift there are several locations that no longer have pedestrian barriers where the sidewalks, curb and gutter have been completed. Please pay attention when traversing the roadway and use identified crossings.

Lewis Street at U.S. 160 is closed to begin underground utility construction. Motorists are encouraged to use 4th Street as an alternative to Lewis Street. The Lewis Street access closure will be in place until late May/early June.

Access to North 5th Street and businesses north of the intersection will be available via 4th Street.

Why will the Lewis Street intersection take several months to complete?
Where Lewis Street intersects U.S. 160 is one of the most difficult intersections the project team is working on. The underground utility work includes demolition and replacement of the geothermal, water and sewer lines from the bottom up. The Lewis Street intersection will then be built back with new ADA-accessible curb and gutter and concrete paving.

Pagosa Springs Middle School information
The Lewis Street and U.S. 160 intersection closure will significantly impact drop-off and pick-up traffic at Pagosa Springs Middle School.

The designated drop-off location on Lewis Street will move from the middle school stairs to the stairs near the district office, closer to the 3rd Street intersection. Please use 2nd and 4th streets for student drop- off and pick-up. Please use extra caution at 4th Street and Lewis Street, as many students walk through this intersection.

Avoid 3rd Street, which is the designated bus route.

How you can help reduce congestion and keep students safe
Ride the bus. We strongly encourage students who are able to take the bus to do so.

Carpool with another family to reduce the number of vehicles near campus. Please be mindful of school buses and help keep bus routes clear so students can arrive safely and on time.

Students walking to school should use the crosswalk at 2nd Street.

Stop before crosswalks, follow all traffic signals and put phones away while driving.

We know this closure may create some inconvenience, and we sincerely appreciate your patience and partnership in helping keep students safe.

Spring/summer construction season
First Street and 10th Street will have flaggers positioned to aid motorists and emergency vehicles during construction.

Work will continue to be contingent upon inclement spring weather events.

Post Contributor

The Pagosa Daily Post welcomes submissions, photos, letters and videos from people who love, and care about, Pagosa Springs, Colorado. More information available at 970-903-2673 or pagosadailypost@gmail.com