Lewis Street intersection
Crews continue to make significant progress on paving operations and the intersection is expected to open mid-week, pending weather delays.
Overlook parking lot
Sidewalk work continues along US 160 next to the Overlook parking lot. Parking spaces will be closed in areas where work is taking place.
North 7th Street
Crews continue potholing and exploratory work. Pedestrians should use street crossing alternative locations at 8th.
South 7th Street
Work will begin with PAWSD scheduled water utility connection updates, followed by safety improvements. Residents should plan on 7th Street being closed through early September.
North 3rd Street intersection
Work continues on the north side of the 3rd Street intersection. Pedestrians may access the north side of Main Street from 4th & Hot Springs crosswalk during the work period.This intersection is expected to open August 15, pending weather delays
100 & 200 blocks
Crews will continue paving the south side of US 160 from 2nd Street East
Pedestrian Safety
Pedestrian crosswalks are open at 4th, 7th, and 8th Streets as an alternative to access businesses along Lewis Street or anywhere on the 400 block. Our team continues to see pedestrians, not practicing good safety measures, jumping barricades and crossing US 160. Our work zone is extremely active in several locations and we want to keep everyone safe!
- Call the project information line: 970-335-9230
- Email the project team: Pagosa160reconstruction@gmail.com
- Visit the project website: www.codot.gov/projects/us160pagosasprings